MILFORD WASTEWATER TREATMENT PLANT          ROOF
REPAIR
Estimated Project Cost: $32,000
Project Description
The project involved
the repair and replacement of the membrane roofing system on three existing
buildings. The existing roofing system was leaking in several spots and had
reached the end of its usable life. A new EPDM membrane roofing system was
installed using existing insulation and flashing wherever possible.
Scope of Work
- Site investigation.
- Vendor coordination.
- Specifications.
- Bidding.
Engineering
Services
- Conceptual design and cost estimate.
- Detailed design and costs estimate.
- Specifications.
- Bid and bid evaluations.
- Construction Assistance.