AIR CONDITIONING UPGRADE
FOR DATA CENTER
Estimated Project Cost: $150,000
Project Description
The Data Center AC Upgrade project involved the
planning, design, installation and startup of two new Computer Room Air Conditioning
(CRAC) units to the existing Data Center at the University of Michigan. These
additional CRAC units were required to ensure that the data center space temperature
could be maintained at the desired set point. This project also involved connecting
these new AC units to the emergency power source.
Scope of Work
- Installation of two (2) new Computer Room Air Conditioning (CRAC) units.
- Installation of a new dry-cooler on roof.
- Installation of glycol piping between CRAC units and dry-cooler.
- Connecting existing emergency power to new CRAC units and dry-cooler.
Engineering
Services
- Conceptual design and cost estimate.
- Preliminary design and cost estimate.
- Detailed design and cost estimate.
- Equipment and instrument specifications.
- Equipment/instrument procurement.
- Bid and bid evaluations.
- Control system design.
- Checkout, startup and commissioning.
- Project cost control.