CHILLED WATER SYSTEM UPGRADE STUDY
Estimated Project Cost: $10,000
Project Description
The Chilled Water System project involved the planning
of long-term equipment repair and replacement for a 16,000-ton chilled water
system at a pharmaceutical manufacturing facility. Recommendations were generated
for sequencing equipment replacement considering installed, maintenance and
operating costs, equipment age, refrigerant phase-out, and future load changes.
This task required the application of lifecycle metrics, refrigeration regulations,
and operating profiles to generate a complete cash flow analysis of various
alternatives.

- Establish criteria for replacement vs. retrofit
- Characterize condition of existing equipment
- Determine appropriate refrigerant phase-out schedules
- Characterize existing operating profiles based on historical data
- Identify probable future load changes
- Characterize efficiency of existing and future equipment
- Create customized software-based life cycle analysis tools
- Identify equipment replacement scenarios
- Quantify life cycle cost impacts for the various scenarios
- Conceptual system design
- Economic analysis
- Application of codes/regulations
- Utility system planning